Operator of a 59-MW wind farm in the Emsland with 13 wind turbines following continuous repowering

WI

Windpark Neudersum GmbH & Co. KG

Dersum (Neudersum), Emsland districtNew on Amplifa

2002Commissioning of the wind farm
13Wind turbines in operation
59 MWTotal rated capacity
ca. 160 million kWh/yearForecast annual energy yield
ca. 240 haWind farm site

About Windpark Neudersum

Windpark Neudersum GmbH & Co. KG operates a wind farm on the land of the municipality of Dersum in the collective municipality of Dörpen in the northwestern Emsland. The wind farm covers an area of around 240 ha within a special designated area for wind turbines and is located near the German-Dutch border. It was commissioned in 2002 with 13 wind turbines of the type Enercon E-66/18.70 by 219 limited partners. Since 2015, as part of several repowering steps, nine of the original turbines have been replaced by more modern units: four Enercon E-101, three Enercon E-126 EP4 and six Nordex N-149 (two in 2023, four in 2025). The 13 turbines in operation have a total rated capacity of 59 MW; the forecast annual energy yield is around 160 million kWh, which, according to the operator, can supply more than 46,000 households. The electricity produced has been fed into the Neudersum substation since completion, which is connected to the TenneT Dörpen-West substation. The commercial and technical operational management is handled by Ems Wind GmbH & Co. KG.

Site
Ihlow
Processes
Operation of wind turbines, Repowering, Electricity feed-in into the Neudersum substation (connected to the TenneT Dörpen-West substation)
Materials
Enercon E-101 (4×), Enercon E-126 EP4 (3×), Nordex N149/5.X/TS125 (2×), Nordex N149/5.X/TCS164 (4×), Enercon E-66/18.70 (dismantled, 9×)
Industries
Wind energy, Renewable energies
  1. 01

    Planning and construction of the wind farm

  2. 02

    Operation of the wind turbines

  3. 03

    Repowering (dismantling and replacement of old turbines)

  4. 04

    Electricity feed-in into the Neudersum substation (TenneT, Dörpen-West)

Turbines and Technology

E-101

Enercon E-101 (4×)

Wind turbine with 3.05 MW, hub height 149 m, rotor diameter 101 m, commissioned 2015/16 as part of the repowering.

E-126 EP4

Enercon E-126 EP4 (3×)

Wind turbine with 4.2 MW, hub height 135 m or 159 m, rotor diameter 126 m, commissioned 2017 and 2018.

N149/5.X/TS125

Nordex N149/5.X/TS125 (2×)

Wind turbine with 5.7 MW, hub height 125.4 m, rotor diameter 149 m, commissioned in October 2023.

N149/5.X/TCS164

Nordex N149/5.X/TCS164 (4×)

Wind turbine with 5.7 MW, hub height 164 m, rotor diameter 149 m, commissioned July/August 2025.

E-66/18.70

Enercon E-66/18.70 (dismantled, 9×)

Original turbines from 2002, progressively dismantled between 2015 and 2025 as part of the repowering.

Location

Neudersum

DE

Wind farm with 13 wind turbines (59 MW)

Materials
Enercon E-101, Enercon E-126 EP4, Nordex N-149
  • 4× Enercon E-101 (3.05 MW, 149 m hub height)
  • 3× Enercon E-126 EP4 (4.2 MW, 135/159 m hub height)
  • 2× Nordex N149/5.X/TS125 (5.7 MW, 125.4 m hub height)
  • 4× Nordex N149/5.X/TCS164 (5.7 MW, 164 m hub height)
  • Neudersum substation with connection to the Dörpen-West substation (TenneT)

Industries

Wind energyRenewable energies

5 Anlagen & Maschinen

MachineManufacturer / modelQuantityWorking areaYear builtSite
Wind turbineEnercon E-1014Hub height 149 m, rotor diameter 101 m, 3.05 MW2015/16Neudersum
Wind turbineEnercon E-126 EP43Hub height 135 m / 159 m, rotor diameter 126 m, 4.2 MW2017/2018Neudersum
Wind turbineNordex N149/5.X/TS1252Hub height 125.4 m, rotor diameter 149 m, 5.7 MW2023Neudersum
Wind turbineNordex N149/5.X/TCS1644Hub height 164 m, rotor diameter 149 m, 5.7 MW2025Neudersum
Wind turbine (dismantled)Enercon E-66/18.709–2002–2023Neudersum

Additional services

Operation of wind turbinesRepoweringElectricity feed-in into the Neudersum substation (connected to the TenneT Dörpen-West substation)

History

  1. 2002

    Commissioning of the wind farm with 13 Enercon E-66/18.70 by 219 limited partners

  2. 2015

    Start of repowering: dismantling of the Enercon E-66, replacement with four Enercon E-101

  3. 2017

    Commissioning of Enercon E-126 EP4 as part of the repowering

  4. 2018

    Further commissioning of Enercon E-126 EP4

  5. 2023

    Commissioning of two Nordex N-149 in October as replacement for two Enercon E-66

  6. 2025

    Commissioning of four more Nordex N-149 in July/August as replacement for the remaining Enercon E-66